Orders for the year 2005
 

GENERAL

Petition  No Petitioner Subject Date of Order Date of hearing
95/2005 Gujarat Urja Vikas Nigam Ltd., Vadodara Direction to NTPC to tie up and procure adequate quantum of Gas at economical rates for Kawas and Gandhar Power Stations and give consent to Gujarat State Petronet Ltd. for laying pipeline in the premises of Kawas and Gandhar Power Stations for supply of gas from Gujarat State Petroleum Corporation Ltd. 17-11-05 17-11-05
18/2005 Power Grid Corporation of India Ltd. Implementation of 400 kV D/C Bina-Nagda-Dehgam transmission lines by Powergrid on the basis of process of approved cost estimate in vogue. 02-08-05 14-06-05
40/2005 Nagarjuna Power Corporation Ltd Approval of tariff of Nagarjuna Power Project (1015 MW) for the period 1.9.2008 onwards. 25-10-05 25-08-05
    Generic Procedure on regulation of power supply to beneficiaries in case of non-payment of dues of Central Power Utilities. 26-12-05  
116/2005 Northern Regional Load Despatch Centre, New Delhi Bringing Bhakra Beas Management Board (BBMB) power stations under the purview of Unscheduled Interchange (UI) mechanism at the regional level 15-12-05 15-12-05
59/2005 Bihar State Electricity Board, Patna Sharing of the transmission charges of the 220 kV D/C Birpara-Salakati transmission line and associated sub-station at Birpara (ER) & Salakati (NER) as inter-regional assets between ER and NER. 14-12-05 8-12-05
89/2002 Power Grid Corporation of India Ltd. Approval of incentive for Transmission System of Eastern Region for the year 2001-02. 16-12-05 6-12-05
129/2005
(Suo Motu) Reimbursement of application fee and publication charges to Central Power Sector Utilities. 22-11-05  
10/2003 GRID Corporation of Orissa Ltd. Payment of outstanding dues by APTRANSCO to GRIDCO for the period from December 1994 to September 1996 25-11-05 22-11-05
Pet in 9/2003 &
11/2003
& 12/2003
GRID Corporation of Orissa Ltd. Payment of outstanding dues by APTRANSCO to GRIDCO for the period from January 2001 to July 2001. & Payment of outstanding dues by APTRANSCO to GRIDCO for the period from October to December 2000 and March-April 2002 & Payment of outstanding dues by APTRANSCO to GRIDCO for the period from September to December 2001 25-11-05 22-11-05
66/2005 Damodar Valley Corporation. Tariff for sale of electricity by Damodar Valley Corporation and the Inter-state Transmission of Electricity.  18-10-05 18-10-05
66/2005 Damodar Valley Corporation Tariff for sale of electricity by Damodar Valley Corporation and the Inter-State Transmission of Electricity 03-11-05 28-10-05
95/2004 PGCIL Prayer for issue of direction to Bihar State Electricity Board for sharing the transmission charges of inter-regional assets. 19-01-05 28-12-04
89/2004 Neyveli Lignite Corporation Limited Levy of transmission charges and applying Regional transmission losses to NLC
Mines.
24-02-05 10-02-05
198/2004 Global Energy Limited Grant of open access for inter-state transmission of electricity. 06-01-05  30.12.2004
18/2005 PGCIL Implementation of 400 kV D/C Bina-Nagda-Dehgam transmission lines by Powergrid on the basis of process of approved cost estimate in vogue. 02-08-05 14-06-05
21/2005 (Suo motu) Development of market in electricity sector. 04-03-05  
6/2004 Madhya Pradesh State Electricity Board Fixation of Wheeling Charges in respect of Transmission System of Grid Corporation of Orissa Ltd. for wheeling of power from NTPC power stations in Eastern Region (ER) through their system to Madhya Pradesh State Electricity Board (MPSEB), Jabalpur with effect from 1.4.2001. 28-07-05 19-07-05
5/2005 Tripura State Electricity Corporation Limited Relief from excessive per unit charge from the hydro electric projects under NEEPCO mainly Ranganadi and Doyang in the post-ABT period, regulation over transmission constraints/contingency/natural calamities causing adverse effect on drawal/trading of power and surrendering of share of Doyang Hydro Electric Project 30-09-05 12-07-05
43/2005 Maharashtra State Electricity Board, Mumbai Petition seeking directions to the Madhya Pradesh State Electricity Board to pay the amounts due to Maharashtra State Electricity Board. 20-09-05  
66/2005 Damodar Valley Corporation Tariff for sale of electricity by Damodar Valley Corporation and the Inter-State Transmission of Electricity 21-06-05 14-06-05
43/2005 Maharashtra State Electricity Board, Mumbai Seeking direction by CERC to the Madhya Pradesh State Electricity Board to pay the amount due to Maharashtra State Electricity Board. 02-08-05 26-07-05
66/2005 Damodar Valley Corporation Tariff for sale of electricity by Damodar Valley Corporation and the Inter-State Transmission of Electricity 29-07-05 26-07-05

Petition No. 9/2003


10/2003


11/2003


12/2003

Grid Corporation of Orissa Ltd.

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from January 2001 to July 2001.

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from December 1994 to September 1996

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from October to December 2000 and March-April 2002

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from September to December 2001

12-07-05 12-07-05
4/2005 National Thermal Power Corporation Limited Renovation and Modernisation of Auraiya Gas Power Station (663.36 MW) 07-07-05 23-06-05
43/2005 Maharashtra State Electricity Board, Mumbai Seeking direction by CERC to the Madhya Pradesh State Electricity Board to pay the amount due to Maharashtra State Electricity Board. 14-06-05 9-06-05
Review Pet No.55/2005
In
Pet No. 196/2004
(Suo motu)
National Hydro Power Corporation Ltd. Review of order dated 28.2.2005 in Petition No.196/2004 (suo motu) - Revision of O&M expenses for the years 2001-02 to 2003-04 09-06-05 07-06-05
    10-02-05  
    Generic procedure on regulation of power supply to beneficiaries in case of non-payment of dues of Central Power Utilities  12-04-05  
9/2003 GRID CORPORATION OF ORISSA LTD. Payment of outstanding dues by APTRANSCO to GRIDCO for the period from January 2001 to July 2001. 21-04-05 21-04-05
6/2004 Madhya Pradesh State Electricity Board  Fixation of Wheeling Charges in respect of Transmission System of Grid Corporation of Orissa Ltd. for wheeling of power from NTPC power stations in Eastern Region (ER) through their system to Madhya Pradesh State Electricity Board (MPSEB), Jabalpur with effect from 1.4.2001. 03-03-05 24.2.2005

9/2003




11/2003

12/2003


10/2003

GRID Corporation of Orissa Ltd.

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from January 2001 to July 2001.

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from October to December 2000 and March-April 2002

Payment of outstanding dues by APTRANSCO to GRIDCO for the period from September to December 2001

Payment of outstanding dues by APTRANSCO to GRIDCO for the period
from December 1994 to September 1996

08-02-05  8.2.2005

 

Tariff


Tariff-Thermal


Coal Based

Petition No

Petitioner

Subject

Date of Order

Date of hearing

IA No.41/2005 in
Petition No.142/2004
IA No.51/2005 in
Petition No.150/2004
IA No.52/2005 in
Petition No.151/2004
IA No.56/2005 in
Petition No.157/2004
National Thermal Power Corporation Ltd. Approval of tariff for Feroz Gandhi Unchahar Thermal Power Station Stage-I (420MW) for the period from 1.4.2004 to 31.3.2009.
Approval of tariff for Feroze Gandhi Unchahar Thermal Power Station Stage-II (420 MW) for the period from 1.4.2004 to 31.3.2009
Approval of tariff of Rihand Super Thermal Power Station (1000 MW) for the period from 1.4.2004 to 31.3.2009.
07-11-05 29-09-05
IA No.40/2005
In Petition No.149/2004
National Thermal Power Corporation Ltd. Approval of tariff of Simhadri Thermal Power Station (1000 MW) for the period from 1.4.2004 to 31.3.2009. 22-12-05 15-12-05
IA No.45/2005
In Petition No.128/2004
IA No.43/2005 In Petition No.146/2004
IA No.50/2005
In Petition No.159/2004
National Thermal Power Corporation Ltd. Approval of tariff of Vindhyachal Super Thermal Power Station Stage-I for the period from 1.4.2004 to 31.3.2009.
Approval of tariff of Vindhyachal Super Thermal Power Station Stage-II for the period from 1.4.2004 to 31.3.2009.
Approval of tariff of Korba Super Thermal Power Station (2100 MW) for the period from 1.4.2004 to 31.3.2009.
22-12-05 22-12-05
122/2005 National Thermal Power Corporation Ltd. Claiming abnormal O&M expenses for Feroze Gandhi Unchahar Thermal Power Station Stage-II for the period 1.4.2001 to 31.3.2004. 08-12-05 08-12-05
IA No.45/2005
In
PetNo.128/2004
National Thermal Power Corporation Ltd. Approval of tariff of Vindhyachal Super Thermal Power Station Stage-I for the period from 1.4.2004 to 31.3.2009. 22-12-05 22-12-05
IA No.40/2005
In Pet No.149/2004
National Thermal Power Corporation Ltd. Approval of tariff of Simhadri Thermal Power Station (1000 MW) for the period from 1.4.2004 to 31.3.2009. 22-12-05 15-12-05
IA No.41/2005 inPet No.142/2004 National Thermal Power Corporation Ltd. Approval of tariff for Feroz Gandhi Unchahar Thermal Power Station Stage-I (420MW) for the period from 1.4.2004 to 31.3.2009. 07-11-05 29-09-05
IA Petition No.39/2005
In Pet No.148/2004

National Thermal Power Corporation Ltd.
Approval of tariff of Ramagundam Super Thermal Power Station (2100 MW) Stage I & II for the period from 1.4.2004 to 31.3.2009. 15-12-05 15-12-05
IA No. 44/2005 in
PetNo.162/2004

National Thermal Power Corporation Ltd.
Petition under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of National Capital Thermal Station, Dadri (840 MW) for the period 1.4.2004 to 31.3.2009. 15-12-05 15-12-05
163/2004 National Thermal Power Corporation Ltd., New Delhi Approval of tariff of Tanda Thermal Power Station (440 MW) for the period 1.4.2004 to 31.3.2009. 13-12-05 13-12-05
139/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Feroze Gandhi Unchahar Thermal Power Station Stage-I 31-03-05 30.11.2004
186/2004 Neyveli Lignite Corporation Limited, Neyveli Fixation of tariff for NLC TPS-I (600 MW) for the period 1.4.2004 to 31.3.2009. 20-10-05 20-10-05
IA No.45/2005 in
Pet No.128/2004
National Thermal Power Corporation Ltd Approval of tariff for Vindhyachal Super Thermal Power Station Stage-I (1260 MW) for the period from 1.4.2004 to 31.3.2009. 02-11-05 27-09-05
5/2002 Neyveli Lignite Corporation Ltd. Revised Tariff for Thermal Power Station II of NLC for the period for 2001-02 to 2003-04. 02-11-05 15-09-05
91/2005 National Thermal Power Corporation Ltd. Revision of norms of Target Availability in respect of Farakka Super Thermal Power Station on account of acute shortage and poor quality of coal during the year 2004-05. 24-10-05 20-09-05
8/2005 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure incurred during 14.1.2000 to 31.3.2004 in respect of Tanda Thermal Power Station (440 MW). 24-10-05 03-03-05
186-04 Neyveli Lignite Corporation Limited, Neyveli Fixation of tariff for NLC TPS-I (600 MW) for the period 1.4.2004 to 31.3.2009. 20-10-05 20-10-05
IA No.19/2005
in Pet No. 56/2005
National Thermal Power Corporation Limited Petition to claim abnormal O & M Expenses not included in the normalised O&M Expenses for Korba STPS for the period 1.4.2001 to 31.3.2004. 26-07-05 26-07-05
83/2005 National Thermal Power Corporation Approval of tariff of Rihand Super Thermal Power Station, Stage-II, unit-I (500 MW) for the period 1.8.2005 to 31.3.2009. 21-09-05 13-09-05
IA No.38/2005 in
PetNo.147/2004
National Thermal Power Corporation Ltd Approval under regulation-86 for transmission tariff for Kayamkulam Combined Cycle Power Project (359.58 MW) for the period from 1.4.2004 to 31.3.2009. 17-10-05 06-10-05
144/2004 National Thermal Power Corporation Ltd Approval of tariff of Talcher Super Thermal Power Station Stage-I (1000 MW) for the period from 1.4.2004 to 31.3.2009. 17-10-05 06-10-05
I.A. 24/2003
in
Petition No. 38/2001
National Thermal Power Corporation Ltd. Generation Tariff for Rihand STPS in Northern Region for the period from 1.4.2001 to 31.3.2004. 06-10-05 29-09-05
74/2005 National Thermal Power Corporation Ltd Petition under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval to allocate capital expenditure on assets of Corporate, Regional and other offices to the capital cost of different stations for the purpose of recovery through tariff. 28-07-05 28-07-05
IA No. 20/2005
in Petition No. 57/2005
National Thermal Power Corporation Ltd. Extension of time for compliance with the CERC order dated 23.6.2005 to file additional data on employee cost element of O&M expenses in respect of Ramagundam STPS Stage I & II. 21-07-05  
8/2005 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure incurred during 14.1.2000 to 31.3.2004 in respect of Tanda Thermal Power Station 440 MW. 03-03-05 03-03-05
195/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges due to additional capitalisation for the period 1.4.2001 to 31.3.2004 in respect of Korba Super Thermal Power Station (2100 MW) 14-07-05 18-01-05
4/2005 National Thermal Power Corporation Limited Renovation and Modernisation of Auraiya Gas Power Station (663.36 MW) 07-07-05 23-06-05
4/2005 National Thermal Power Corporation Limited Renovation and Modernisation of Auraiya Gas Power Station (663.36 MW) 02-02-05  25.1.2005
10/2005 National Thermal Power Corporation Ltd, New Delhi Tariff for Unit-I of Riihand Super Thermal Power Station Stage-II.
Tariff for infirm power supply prior to the date of commercial operation.
National Thermal Power Corporation Ltd, New Delhi
10-03-05 10.3.2005
40/2005 Nagarjuna Power Corporation Limited Approval of tariff of Nagarjuna Power Corporation Limited (1015 MW) for the period 1.9.2008 onwards. 14-07-05 14-07-05
190/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges due to additional capitalisation for the period 1.4.2001 to 31.3.2004 in respect of Singrauli Super Thermal Power Station (2000 MW) 07-07-05 27-07-05
19/2005 National Thermal Power Corporation Ltd. Revision of rate of infirm power supplied from Ramagundam Super Thermal Power Stations Stage-III approved vide order dated 31.8.2004 in Petition No. 63/2004. 10-05-05 26-04-04
173/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges due to additional capitalisation for the period 1.4.2001 to 31.3.2004 in respect of Ramagundam STPS ( 2100MW) 03-05-05 13-01-05
174/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Anta Gas Power Station 13-4-05 13-1-05
169/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Vindhyachal Super Thermal Power Station Stage – I. 13-04-05 13-1-05
167/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Dadri Gas Power Station 13-04-05 13-1-05
161/2004 NTPC Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Faridabad Gas Power Station. 07-04-05 23-12-04
154/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Vindhyachal Super Thermal Power Station Stage – II. 04-04-05 23-12-04
143/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Feroze Gandhi Unchahar Thermal Power Station Stage-II 04-04-05 30.11.2004
165/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.3.2003 to 31.3.2004 in respect of Simhadri Thermal Power Station. 04-04-05 23.12.2004
141/2004 National Thermal Power Corporation Ltd. Approval of revised fixed charges on account of additional capital expenditure for the period 1.4.2001 to 31.3.2004 in respect of Kayamkulam Gas Power Station 04-04-05 30.11.2004
40/2004 Badarpur Thermal Power Station, New Delhi Approval of tariff of Badarpur Thermal Power Station (705 MW) for the period from 1.4.2004 to 31.3.2009. 26-07-05  
40/2004 Badarpur Thermal Power Station, New Delhi Approval of tariff of Badarpur Thermal Power Station (705 MW) for the period from 1.4.2004 to 31.3.2009. 07-07-05 15-06-05
40/2004 Badarpur Thermal Power Station, New Delhi Approval of tariff of Badarpur Thermal Power Station (705 MW) for the period from 1.4.2004 to 31.3.2009. 01-04-05  
40/2004 Badarpur Thermal Power Station, New Delhi Approval of tariff of Badarpur Thermal Power Station (705 MW) for the period from 1.4.2004 to 31.3.2009. 25-05-05 16-05-05
98/2002 National Thermal Power Corporation Ltd. Approval of revised fixed charges from 1.4.1997 to 31.3.2000 based on additional capitalisation and effect of Foreign Exchange Rate Variation and revised tariff from 1.4.2000 to 31.3.2001 for Kahalgaon Super Thermal Power Station 09-05-05  
1/2003 National Thermal Power Corporation Ltd. Petition for approval of tariff of Unit 1& II of Talcher STPS Stage-II (4x500MW) 13-06-05 07-10-04
5/2002 Neyveli Lignite Corporation Ltd. Revised Tariff for Thermal Power Station II of NLC for the period from 2001-2002 to 2003-2004. 03-05-05 21-04-05
40/2004 Badarpur Thermal Power Station, New Delhi Approval of tariff of Badarpur Thermal Power Station (705 MW) for the period from 1.4.2004 to 31.3.2009. 29-04-05 21-04-05
Review Pet No. 28/2005 in Pet No. 194/2004 TAMIL NADU ELECTRICITY BOARD Fixation of tariff for Neyveli Thermal Power Station-I (600 MW) for the period 1.4.2002 to 31.3.2004 21-04-05 21-04-05
IA no. 48/2004
and no. 50/2004
in Pet No.
40/2004
Badarpur Thermal Power Station, New Delhi Approval of tariff of Badarpur Thermal Power Station (705 MW) for the period from 1.4.2004 to 31.3.2009. 10-03-05 10-03-05
5/2002 Neyveli Lignite Corporation Ltd. Revised Tariff for Thermal Power Station II of NLC for the period from 2001-2002 to 2005-2006. 03-03-05 3.3.2005
194/2004 Neyveli Lignite Corporation Ltd Non-compliance of the Commission’s order dated 31.8.2004 by TNEB in respect of fixation of tariff for Thermal Power Station-I (600 MW) for the period from 1.4.2002 to 31.3.2004. 01-02-05 27.1.2005
91/2004 National Thermal Power Corporation Ltd Approval of tariff of Talcher Thermal Power Station (460 MW) for the period from 1.4.2004 to 31.3.2009. 27-01-05 27.1.2005
179/2004 National Thermal Power Corporation Ltd. Petition for approval of tariff for power supplied from Talcher STPS Stage-II (4x500 MW) for the period 1.4.2004 to 31.3.2009. 14-01-05 28.12.2004
         

ii)Gas Based

Petition  No

Petitioner

Subject

Date of Order

Date of hearing

114/2005 National Thermal Power Corporation Ltd. Revision of O&M expenses for the period 1.4.2001 to 31.3.2004 in respect of Gandhar Gas Thermal Power Station (657.39 MW). 02-11-05 28-10-05
IA No. 42/2005 in Pet No. 155/2004 National Thermal Power Corporation Ltd. Petition under Section 62 and 79(1) (a) of the Electricity Act, 2003 read with Chapter-V of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 for approval of tariff of Dadri Gas Power Station (829.78 MW) for the period 1.4.2004 to 31.3.2009.. 04-10-05 24-10-05
IA No.47/2005 in Pet No. 160/2004 National Thermal Power Corporation Ltd. Interlocutory application for amendment of tariff calculations enclosed to the Petition No.160/2004 for approval of tariff of Anta Gas Power Station (419.33 MW) for the period 1.4.2004 to 31.3.2009. 04-10-05 24-10-05
32/2003 North Eastern Electric Power Corporation Ltd. Approval of tariff in respect of Agartala Gas Turbine Power Project for the period from 1.4.2001 to 31.3.2004.