BEFORE THE CENTRAL ELECTRICITY REGULATORY COMMISSION
NEW DELHI
Application No.9/2000 in Petition No.14/2000
Present:
In the matter of
Approval for Transmission Tariff and Miscellaneous Application for ad interim order for 400 KV S/C Korba Raipur Transmission Line, loop in loop out of Korba Bhilai and Bhilai Chanderpur lines and 315 MVA ICT (I & II) and associated bays in WR.
AND
In the matter of :
M/s. Power Grid Corporation of India Ltd.,
B-9, Qutab Institutional Area,
Katwaria Sarai,
Petitioner
New Delhi-110 016.
The following were present :-
ORDER
(Date of Hearing 24.04.2000)
This petition has been filed by Power Grid Corporation of India Ltd., (PGCIL) seeking approval of the Commission for Transmission Tariff and an Interlocutory Application for ad interim order for 400 KV S/C Korba Raipur Transmission Line, LILO of Korba Bhilai transmission line and 315 MVA ICT (I & II) and associated bays in WR, in commercial operation since 1/1/2000 and LILO of Bhilai- Chanderpur transmission line and 315 MVA inter-connecting transformer with associated bays at Raipur which were expected to be commissioned w.e.f. 1/4/2000. The petitioner has also filed an IA (No.8/2000) for interim order in its favour till final determination of tariff by the Commission and disposal of the main petition.
2. According to the petitioner, Government of India had approved implementation of the transmission projects under Vindyachal Stage-II transmission system in Western Region, at an estimated cost of Rs.657.71 crore, including IDC of Rs.110.29 crores. Subsequently the scope of work was modified and such modifications were agreed to by the constituents in a meeting held on 26th September, 1996. The scope of the work as finally undertaken by the petitioner was as under:
3. The petitioner has already built in the following assets, at an estimated cost of Rs.434.27 crores:-
4. The above noted assets are under commercial operation since 1st August, 1999. The Commission had already allowed the petitioner to charge transmission tariff on provisional basis for these assets vide its Order dated 30/11/99 in Petition No.10/99.
5. The estimated completion cost of the assets noted in para 1 above, as per audited certificate is Rs.16,116.09 Lakhs in respect of the assets which were put to commercial operation w.e.f. 1.1.2000 and Rs.2993.22 lakhs for the assets put to commercial operation w.e.f 1.4.2000. The tariff proposal was discussed by the petitioner with the respondents. It has been observed from the minutes dated 10th January, 2000 that the respondents had agreed to make provisional payment at the rate of 90% of the tariff calculation circulated by the PGCIL, subject to adjustment after approval of the final tariff by the Commission.
8. Shri Sachdev appearing for the petitioner explained that it was not open to the PGCIL to reduce the approved cost of the project and it was within the purview of CEA/Ministry of Power. He, however, conceded that it was obligatory for the PGCIL to take up the matter with CEA/ Government of India for proportionate reduction in the cost as well as interest, though he maintained that the estimated completion cost of the project was within the ceiling of the original approved cost. He had also clarified that minor delay in the implementation of the project was due to non-cooperation on the part of the SEBs in timely shut down of the system.
Sd/-
Sd/-
Sd/-
Sd/-
(A.R. Ramanathan)
(G.S. Rajamani)
(D.P. Sinha)
(S.L. Rao)
Member
Member
Member
Chairman
New Delhi dated the 24th April, 2000.