12. At this stage we may note that a  notice was issued to the Government of India since the Commission felt the  necessity to provide it an opportunity of hearing.  Although no one appeared before the Commission on behalf of the Govt. of India, it has clarified vide its letter No.2/3/Powergrid/Tariff/99 dated the 14th December, 1999 that the tariff notifications for four regions of Powergrid Transmission System were issued during the period from 20.7.1998 to 4.12.1998 in pursuance to the main notification containing the general principles and norms for fixation of transmission tariff issued during December, 1997. These notifications have provision for payment of incentive for Availability of the system beyond 95 percent.  On the question of notification dated 4.2.1999, regarding “Certification of Availability by REB” it is clarified that similar provision exists in case of NHPC and NTPC generation tariff notifications also, which has been accepted by the beneficiaries. 

13. The Commission also obtained the opinion of the learned Attorney General of India who has opined that the Commission has jurisdiction and authority to adjudicate upon the issues relating to fixation of tariff, and other incidental matters for the period prior to 15.5.1999.  It has been further advised by the learned Attorney General that until fresh regulations are published, the Commission may adjudicate issues in the light of guidelines notified by the Central Government in the matter of fixation of tariff from time to time and prior to 15.5.1999.  The copy of the opinion of the learned Attorney General was circulated amongst the parties present for hearing on 8.2.2000 for their reaction to the views recorded by him.  None of the parties during the hearing disputed the correctness of the views recorded by the learned Attorney General though in their original pleadings some of them expressed the opposite views.

14. The petitioner and some of the respondents (MPEB in petition No. 13/99, APTRANSCO and TNEB in petition No. 14/99 and UPPCL and PSEB in petition No. 16/99) have filed their written submissions on the preliminary legal issues.  We have heard Shri P.Tripathi, Senior Counsel on behalf of the petitioner and the representatives of the respondents at  great length.  We proceed to record our findings on the preliminary legal issues framed by us.

Issue No. (a)

Validity of he transmission tariff notified by the Central Government after establishment of the Commission.

15. As we have already noted, the general principles and norms for fixation of tariff of the transmission system were notified by the Central Government on 16.12.1997.  The respondents have not questioned the validity of this notification.  We are of the opinion that the said notification dated 16.12.1997 cannot be faulted with.  Accordingly, this notification is held to be valid and intra vires of the Central Government.

16. The real dispute relates to the validity of the tariff notifications issued by the Central Government after the establishment of the Commission.  The Commission was constituted in terms of notification of the Central Government dated 24.7.1998.  The function to regulate the inter-state transmission of energy, including tariff of the transmission utilities has been assigned to the Commission in terms of Section 13(c) of the Regulatory Commissions Act.  The amended Section 41 of the Supply Act, which came into effect w.e.f. 31.12.1998, makes it further explicit that after its establishment, the Central Commission is conferred the exclusive jurisdiction to determine the charges payable to the Central Transmission Utility in case of the inter-state transmission system.  Shri P.Tripathi, the learned Senior Counsel appearing for the petitioner sought to justify the notifications issued by the Central Government after establishment of the Commission, by invoking Section 43A (2) of the Supply Act.  According to the learned Counsel, the petitioner is a “Generating Company” within the meaning of the term defined under section 2(4A) of the Supply Act, since it has amongst its objects the establishment, operation and maintenance of generating stations.  As a generating company, one of the duties assigned to the petitioner under section 18A of the Supply Act, is to establish, operate, maintain the generating stations and its lines, sub-stations and main transmission lines connected therewith.  Therefore, it was contended that the tariff of the transmission system owned and controlled by the petitioner had to be fixed in terms of section 43A(2) of the Supply Act.  This section has been omitted by the Central Government w.e.f. 15.5.1999.  The learned counsel for the petitioner has argued that the Central Government had jurisdiction and power to determine tariff of the transmission system owned by the petitioner before omission of Section 43A (2) of the Supply Act as sale can be through transmission which is fundamental  and an aspect of generation.

17. Before we proceed to examine the contention raised on behalf of the petitioner, we consider it appropriate to have a look at  section 43 A(2) of the Supply Act as it stood prior to its omission and is, therefore, reproduced below:-

43.A.            Terms, conditions and tariff for sale of electricity by Generating Company:

(1)  …………………………………….

(2)  The tariff for the sale of electricity by a Generating Company to the Board shall be determined in accordance with the norms regarding operation and the Plant Load Factor as may be laid down by the Authority and in accordance with the rates of depreciation and reasonable return and such other factors as may be determined, from time to time, by the Central Government, by notification in the Official Gazette:

Provided that the terms, conditions and tariff for such sale shall, in respect of a Generating Company, wholly or partly owned by the Central Government, be such as may be determined by the Central Government and in respect of a Generating Company wholly or party owned by one or more State Governments be such as may be determined, from time to time, by the government or governments concerned.

18. A mere look at Section 43A(2) of the Supply Act shows that it authorises the Central Government to determine the terms, conditions and tariff for “sale of electricity” in respect of a generating company, owned by it.  The petitioner is engaged in the business of “transmission of electricity.”  The “transmission of electricity” by the petitioner, in our opinion, cannot be equated with “sale of electricity”.  According to  Black’s Law Dictionary, “sale” means

“a contract between two parties called respectively, the “seller” (or vendor) and the “buyer” (or purchaser) by which the former, in consideration of the payment or promise of payment of certain price in money, transfers to the latter the title and the possession of property or a contract whereby property is transferred from one person to another for a consideration of value, implying the passing of the general and absolute title, as distinguished from a special interest falling short of complete ownership.

An agreement by which one gives a thing for a price in current money and other gives the price in order to have the thing itself.”

Therefore, in order to constitute “sale” it must involve transfer of title from the “seller” to the “buyer”.  The petitioner does not have the title to electricity being transmitted or transferred by it.  The title to electricity vests either in the generator of electricity or the beneficiary.  The role of petitioner in the process of transmission of electricity is akin to that of a carrier.  As we have noticed earlier, the region-wise tariff notifications were issued by the Central Government under Section 41 of the Supply Act and not under Section 43A(2) thereof.  It would further show that at the time of issue of region-wise tariff notifications the Central Govt. itself had never contemplated that these were being issued under Section 43A (2) of the Supply Act.  We may also note that the reliance placed by the learned Counsel for the petitioner on Section 18A of the Supply Act does not take him too far for the reason that it was inserted in 1976 whereas Section 43A was introduced  in 1991 when transmission and generation came to be recognised as separate activities.

19. In the light of the above discussion, we hold that the Central Government was divested of its jurisdiction to determine tariff of inter-state transmission utilities after establishment of the Central Commission.  It was only the Central Commission that was vested with power and jurisdiction to regulate tariff of the transmission utilities involved in inter-state transmission of electricity.  Therefore, we hold that the notifications issued by the Central Government after the establishment of the Central Commission are liable to be held as  invalid and ultra vires the Electricity Regulatory Commissions Act 1998 and Electricity (Supply) Act 1948.  However, in terms  of its regulatory powers, the Commission is competent to lay down its own norms and principles for tariff determination which it has yet to do.  Therefore, in the interest of continuity  and to avoid a situation of vacuum, we consider it expedient to adopt the norms laid down by the Central Government for the purpose of these petitions.

Issue No. (b):

Whether the notification of incentive is a matter of procedure or that of substantive law and as such can be taken up by the Commission even for the period prior to vesting of jurisdiction in it under the ERC Act.

20. According to the learned counsel for the petitioner, incentive/disincentive is an integral component of the transmission tariff payable in accordance with the principles and the formula given in the notifications.  It has been contended that in the circumstances, the notification of incentive is simply a matter of procedure involving determination of the exact value and does not involve any substantive law.

21. MPEB in its reply has stated that by virtue of agreement dated 31.3.1999, incentive can be notified by the Central Government for the period prior to the vesting of jurisdiction in the Commission.  TNEB has averred that the Commission does not have jurisdiction to notify incentive for the period prior to its establishment in July, 1998.  On the other hand, according to UPPCL and PSEB, the jurisdiction to decide issue regarding tariff for any period lies with the Commission, since incentive is a component of tariff.

22. Consequent to the establishment of the Commission and vesting in the power for determination of tariff by law, the Central Government gets divested of jurisdiction to determine the incentive payable.  Therefore, it is futile to contend on behalf of the respondents that the Commission cannot exercise its jurisdiction to notify tariff.  However, we are not persuaded to accept the contention of the petitioner that notification of tariff by the Commission is only a matter of procedure.  This would mean acceptance of previous norms which ipso facto cannot be applied.  If law prescribes the terms and conditions, the mere change of forum on same norms may be a mere procedure.  On the contrary, the Commission is to lay down the terms and conditions of Tariff.  Thereafter the Tariff has to be determined by following due process of hearings. The respondents, against whom the claim for incentive lies have to be  afforded  an opportunity of hearing and their objections, if any, have to be adjudicated upon. The Commission has to determine the admissibility and propriety of the claim for incentive in the light of the laid down principles.   We are of the firm opinion that the notification of incentive is not merely a matter of procedure and as it involves adjudication of the rights of the parties, it is matter of substantive law and as such the Commission cannot mechanically determine the incentive.                   

Issue No. (c):

Whether the Commission has jurisdiction to exercise the same powers as were exercisable by the Central Government regarding determination of incentives for use of inter-state transmission system, before establishment of the Central Commission.  

Issue No. (e):

Whether the Commission can exercise jurisdiction for notifying incentive for the period prior to its establishment

Issue No. (g):

 Whether the Commission is to follow the criteria laid down by the notifications of the Central Govt. regarding payment of incentive.  

23. According to the petitioner, the Commission has jurisdiction to exercise the same powers as were exercisable by the Central Government regarding determination of incentive for use of the inter-state transmission system, before its establishment and has jurisdiction to notify the incentive that is part of tariff.   The respondents have expressed divergent views on these issues.  MPEB, in its written submissions has raised an objection to the claim made by the petitioner.  According to MPEB, the Commission cannot exercise powers under the notification issued by the Central Government.  According to the learned counsel for the petitioner, the Commission has jurisdiction to notify the incentive that is a part of tariff.  On the other hand, the respondents have expressed divergent views on the issue.  According to APTRANSCO and UPPCL, the Commission can exercise jurisdiction for notifying the incentive amount payable to the petitioner for the period prior to its establishment.   PSEB has contended the tariff determination by the Commission w.e.f. 1.4.1997 is pre-requisite to claim incentive. 

24. Under Section  28  of  the  Regulatory Commission Act, the Commission is empowered to determine by regulations the terms and conditions for fixation of tariff.  The Commission is already in the process of finalising the tariff norms and these will be notified in due course of time. It has been contended by the respondents that the Commission, should in the first instance notify the terms and conditions for tariff under section 28 of the Regulatory Commissions Act and these terms and conditions may apply for the period the incentive is claimed since the Commission has unfettered powers and jurisdiction under the law.   The arguments advanced by the respondents do not really change the extent of jurisdiction for the prior period but support the petitioner’s case that the Commission can exercise jurisdiction with the rider that these would be on the terms and conditions of the Commission.  This, however, is not the real issue.  Parties, therefore, do not disagree on jurisdiction per se.  However  as a matter of abundant caution, the Commission itself took up with the Central Government to exercise its powers under Section 60 of ERC Act to clarify by notification that the Commission’s jurisdiction extends to all matters relating to past periods as well when the Commission was established.  The clarification was not forthcoming from the Government. To be on the safe side, the Commission called for an opinion from the learned Attorney General of India in this regard. The learned Attorney General  has specifically stated that until regulations are published by the Commission, the Commission may adjudicate these issues in the light of guidelines notified by the Central Government in the matter of fixation of tariff from time to time and prior to 15th May 1999.  We are guided by the opinion of the learned Attorney General (the correctness of which remains undisputed) that until fresh regulations are published by the Commission, it may adjudicate issues in the light of guidelines notified by the Central Government since otherwise it may create uncertainties in the mind of the parties.   The above conclusion draws support from the statutory provisions contained in Regulation 79 of the CERC (Conduct of Business Regulations framed by the Commission and the notification dated 12.5.1999 issued by the Commission. The notification of 12.5.99 specifically provides that the tariff of such generating companies, existing on 15.5.99, will continue to be charged for the period for which it was approved or till any further order in this regard is passed by the Commission, whichever is earlier.

< next page >


[Home] [About Us] [Extracts of Acts]
[Regulations][Orders] [Publications] [Power Data] [Annual Report]
[Schedule of Hearings][Bulletin Board] [Jobs] [Contact Us] [Search] [Links]