|
CENTRAL
ELECTRICITY REGULATORY COMMISSION PRESS
RELEASE-1.11.1999 INDIAN
ELECTRICITY GRID CODE India began to develop an inter-state
transmission system (ISTS) to enable electricity to flow over the country
as a whole, only about two years ago. The system has been severely
stretched because of inadequate transmission capacity. One result for
example is that surplus power of the East can only be partly sent to
deficit areas in the South. The Grid Code tries to bring discipline in the
operation of the ISTS so as to enable power to flow at an optimum level
while maintaining good quality, which is not the case today. The CERC had
issued on 31st March, 1999, directions to the central transmission utility
(Powergrid) to prepare the Indian Electricity Grid Code. A draft was
submitted on 11 June, 1999. This was widely circulated for public comment.
CERC held hearings in July '99 and a large number of comments were
received and considered. The CERC has issued an order on 30th
October, 1999 to the CTU to submit the final Indian Electricity Grid Code,
incorporating the directions of the order, within two weeks. They have
been given time till the rest of this year to hold meetings and correspond
with all constituents of the inter-state transmission system, to make them
familiar with the various provisions. The IEGC will come into effect from
the 1st January, 2000. Being
an order of the Commission, violations will be treated as violations of
the Commission's orders and subject to penalties. The Grid Code contains many detailed
provisions. The highlights are: A chapter on transmission licensing is to
be submitted separately, which will keep in view the urgent need for the
huge investment in transmission and to mobilise private and public
resources. Powergrid will submit this chapter to CERC, in which the whole
process of transmission investment will be transparent. Till that is done,
the CTU shall invest on new lines through a transparent process,
announcing its intention to make investment on any new lines, setting out
in full the details of such investment including the costs, time and tasks
involved. It shall allow at least a month for objections or alternative
proposals to be submitted. In case such are received within the given
time, they shall be submitted to CERC for consideration and final disposal
before taking up the new investment. When the chapter on transmission
licensing is incorporated or announced separately by the Commission that
shall then be in force. The order also specifies the respective
roles of RLDCs and other constituents of the system. It asks all concerned
including the Central Electricity Authority to take cognizance of the
changed legal provisions subsequent to the ERC Act 1998, and the
amendments in 1998 to the Indian Electricity Acts of 1910 and 1948. The
CTU and Regional Load Despatch Centres (RLDCs) should be allowed to play
the roles, assigned to them and accept responsibility as per law. The
constructive role played by CEA in the operation of the ISTS is now vested
in the CTU. The law also redefines the roles of REBs. The order asks the CTU to suitably man
RLDCs with senior functionaries so as to effectively discharge their
independent responsibilities. CTU operations including the RLDCs should be
under the charge of an independent full time Director of Powergrid so that
it may be seen separately within Powergrid. There shall also be a monitoring
committee at the CTU which shall cover all the 5 RLDCs. This Committee
shall periodically monitor the functions of the RLDCs and review their
directions, as well as compliance/non-compliance by the concerned
agencies. This Committee shall consist of the Chairman, Powergrid as
Chairman, Chairman of all REBs, and one representative from the generating
companies owned or controlled by the Central Government. In order to keep the RLDCs operating in a
transparent fashion, RLDC accounts will be independently audited. In many
countries the CTU functions of system operation incorporating those of
RLDCs and REBs, are performed by a non-profit independent system operator
(ISO). Our present legal framework does not provide for this. This is why
we have tried to structure the functioning of the RLDCs in a manner, which
is open and transparent, and accountable to a collective forum. As far as planning is concerned, the role
of the CTU has to be in conformity with the perspective plan and the
planning criteria and guidelines issued by the CEA. It shall be the
responsibility of the CTU to revalidate on an annual basis the studies in
the short term of five years, by incorporating realistic assessment of
generation addition, load growth and delay if any, in actual execution of
transmission lines. The main part of the Grid Code relates to
connection conditions, operating procedures and scheduling and despatch. The CERC has directed that the CTU must
ensure that constraints that restrict merit order despatch, are removed.
The scope of the connection code extends also to the CTU. The CTU will
within one month of an application being received by it, seeking
connection/ modification, shall specify the details of the connection. The
CTU will announce the draft prepared on the lines suggested by the CEA and
approved by the Commission to be annexed to the IEGC before release. Frequency variations are at extreme
ranges in India, from as low as 48 in the South to 53.5 in the East. This
is against the range of 48.5 to 50.5, provided in the Indian Electricity
Rules even though the world over, the frequency is set to be stabilised at
50 hertz. In order to move towards a more stable frequency regime, CERC
has directed that free governor action shall resume immediately in thermal
units with capacity of 200 Mw and above, and all reservoir based hydro
stations. For others, the CTU may separately announce the time limit. Some
exceptions are made for nuclear power stations in view of their safety
requirements. Another major problem in the quality of
electricity supply in India has been the extreme voltage fluctuations.
This is largely due to the inadequacy of reactive power compensation. The
Grid Code provides for adequate charges towards provision of reactive
power at the cost of real power. It is expected that SEBs and distribution
companies will soon begin to provide adequate reactive compensation. The Grid Code will aim to minimise sudden
variations in voltage and frequency due to loss of generation and load. The Regional Load Despatch Centres shall
report instances of persistent non-compliance of the Grid Code. In case of
non-compliance, a penalty system will be enunciated as per the Act, and in
case of disputes, CEA will be the first level arbitrator, followed by the
CERC. The commercial accounting of inter-state
transactions in power will continue to be done by the Regional Electricity
Boards. The Grid Code will spell out the detailed scheme for metering
which shall be the responsibility of the RLDC. Any over drawal or under drawal beyond
the scheduled despatch will be subject to penalties which could be in the
form of extra tariff to be notified separately, regulation of power, and
other penalties available to CERC under the Act. The Grid Code also provides for a
periodical review of the Grid Code so that it remains dynamic in relation
to the changing conditions in the system. The first review will commence
in March, 2000. |
[Home] [About Us] [Extracts of Acts]
[Regulations][Orders] [Publications] [Power Data] [Annual Report]
[Schedule of Hearings][Bulletin Board] [Jobs] [Contact Us] [Search]
[Links]