ANNEXURE-II
Formulae for calculation of Availability of each category of transmission elements
o
/ 0
AVo(Availability of o no. of AC lines) =
å Wi(Ti
-TNAi) / å Wi
i=1
Ti / i=1
p
/ p
AVp(Availability of p no. of HVDC pole) = å Wj(Tj -TNAj) / å Wj
j=1 Tj
/ j=1
q
/ q
AVq(Availability of q no. of ICTs) = å Wk(Tk - TNAk) / å Wk
K=1 Tk
/ k=1
r
r
AVr(Availability of r no. of SVCs) = å 0.5WIl (TIl -TNAIl)
+ å 0.5 WCl (TCl TNACl)
l=1 TI
l l=1
TCl
-------------------------------------------------------------
r
r
å 0.5WIl + å 0.5 WCl
i =1
l=1
/ s
AVs(Availability of s no. of Switched = å Wm(Tm-TNAm)
/ å Wm
Bus reactors)
Tm / m=1
AVt (Availability of t no. of HVDC = å Wn(Tn-TNAn) /å Wn
Back-to-back Blocks) n =1 Tn n =1
Where Wi = Weightage factor for ith transmission line
Wj = Weightage factor for jth HVDC pole
Wk = Weightage factor for kth ICT
WIl & WCl = Weightage factors for inductive
& capacitive operation of lth SVC
Wm = Weightage factor for mth bus reactor
Wn = Weightage factor for nth HVDC back to back block
Ti, Tj, Tk, TIl, TCl, -
The total hours of ith AC line, jth HVDC pole, kth
ICT, lth SVC (Inductive
Tm & Tn Operation), lth SVC (Capacitive Operation), mth
Switched Bus Reactor & nth HVDC back-to-back block during the period
under consideration (excluding time period for outages not attributable to POWERGRID for
reasons given in Para 6 of the procedure)
TNAi , TNAj , TNAk - The
non-availability hours (excluding the time period for outages not
TNAIl, TNACl, TNAm,
attributable to POWERGRID taken as deemed availability as per Para 5 of TNAn
the procedure) for ith AC line, jth HVDC pole, kth ICT
, lth SVC (Inductive Operation), lth SVC (Capacitive
Operation), mth Switched Bus Reactor & nth HVDC
back-to-back block .